Display Settings Command on the S1 // Projects Tab

Set time units and the currency symbol.

Duration Time Unit

Field/Option Description
Hours Select this option to display all duration time fields in hours.
Days Select this option to display all duration time fields in days.

Work Time Unit

Field/Option Description
Hours Select this option to display all work time fields in hours.
Days Select this option to display all work time fields in days.

Elapsed Durations Time Unit

Field/Option Description
Hours Select this option to display all work time fields in hours.
Days Select this option to display all work time fields in days.
Weeks Select this option to display all work time fields in weeks.

Culture

Field/Option Description
Currency Symbol Enter the currently symbol that you want to use in the Activity view.